Update: September 21, 2023

University Drive bridge closed Saturday, September 23.

To help with pedestrian safety as our community celebrates Homecoming 2023 certain campus roadways, including the University Drive bridge will be closed to vehicles on Saturday, September 23.

Full details can be found on through Parking Services.


Previous Updates

September 14, 2023

University Drive bridge to close Wednesday, September 20 for lighting repairs and upgrades

University Drive bridge will be closed to vehicles on Wednesday, September 20 (rain date Sept. 21) from 6 a.m. to 6 p.m. for lighting repairs and upgrades.

During the closure, pedestrians will be restricted to one sidewalk. Cyclists will be required to walk their bikes across the bridge on the sidewalk. Drivers are asked to enter campus using Western Road or Windermere Road.

LTC bus service changes
Transit users are asked to visit the LTC website for schedule updates and detour information.

August 9, 2023

University Drive bridge to close to vehicles August 15 for annual inspection

University Drive bridge will be closed to motor vehicles on August 15 from 6 a.m. to 6 p.m. (rain date August 16) for an annual inspection.

During the closure, pedestrians will be restricted to one sidewalk. Cyclists will be required to walk their bikes across the bridge on the sidewalk.

View the Service Interruption Notice

March 4, 2022

University Drive bridge to close to vehicles for one day for annual inspection

University Drive Bridge will be closed to motorized vehicles on March 14, 2022 from 6:00 a.m. to 6:00 p.m. for an annual inspection.

During the closure, pedestrians will be restricted to one sidewalk. Cyclists will be required to walk their bikes across the bridge on the sidewalk.

October 19, 2020

THE UNIVERSITY DRIVE BRIDGE WILL BE TEMPORARILY CLOSED TO ALL MOTORIZED VEHICULAR TRAFFIC

Motorized vehicles will be prohibited from crossing University Drive Bridge on November 3, 2020 (rain date November 4) to allow inspectors to review work completed in 2019. The bridge will reopen prior to the next business day.

During the closure, pedestrians will be restricted to one sidewalk. Cyclists will be required to dismount and integrate with pedestrian flow.

LTC bus service changes

Updates and detours are posted on the LTC website; http://www.londontransit.ca/category/detours/

March 7, 2019

University Drive Bridge reopens to motorists on the morning of Friday, March 8.

The bridge has been closed since October following an inspection that showed the bearings required immediate attention. Severe weather throughout February slowed the pace of repairs, however, only delayed the reopening by a week. During the closure, the bridge remained open to accommodate pedestrian and cyclist traffic.

London Transit schedule will return to regular routing; https://realtime.londontransit.ca/#/app/nextdepartures

The crossing remains a shared roadway and vehicles will still not be permitted to pass bicycles anywhere on the bridge.

February 20, 2019

The opening of University Drive Bridge to motorists is now scheduled to take place on Friday, March 8.

Early February's severe weather — including freezing rain, snow, and extreme cold — slowed the pace of repairs and delayed the reopening by a week. Particularly during the freezing rain, work had to slow down or even halt for a few days to ensure worker safety,” said Elizabeth Krische, Western’s Associate Vice-President (Facilities Management).

The bridge has been closed to all but pedestrians and cyclists since October 18 after an inspection showed deterioration in the bearings that help the bridge to flex under load in fluctuating temperatures.

In an effort to open the bridge as soon as possible, contractors have been working 10- and 12-hour days.

Bearings on both ends of the bridge have been replaced, but there are still 590 rivets to be removed — each of them six centimetres long, and original to the 95-year-old bridge — so that the bridge can be jacked and the centre-span bearings replaced.

Cars, trucks, ambulances and regular-sized transit and shuttle buses will be able to resume using the bridge. However, a 12-tonne load limit will remain in place that prohibits concrete trucks and fire trucks from crossing.

Upon re-opening, the bridge remains a shared roadway and vehicles will still not be permitted to pass bicycles anywhere on the bridge.

January 3, 2019

Following the in-depth bearing inspection in November, work to repair the bridge will commence on Monday, January 7. During the work, the bridge is expected to remain open with some restrictions. Pedestrians will use the walkways along the outside of the deck and cyclist will have access to a section of the roadway. Equipment and supplies lay down space will take most of the roadway west of the bridge. Work is expected to be completed by March 1, 2019.

Video Update: November 16

Following the advice of a structural engineering firm, Western University closed University Drive Bridge to all motorized vehicles effective October 18, 2018. The bridge remains open to pedestrians and cyclists. On November 12, an in-depth inspection of the bridge was conducted using a BridgeMaster. The results of the inspection will help guide the repair design and is estimated to be completed in the weeks following. Once the design has been approved, a contractor specializing in bridge repair will be selected to complete the work. It is estimated the work itself could take months and completion of the project will occur in the new year. [View on Youtube]

vehicles can access main campus via Perth Dr, Lambton Dr. and Philip Aziz Ave.

November 8, 2018

Pedestrians crossing University Drive Bridge will be restricted to one sidewalk on Monday only, while detailed inspection of the 95-year-old structure takes place. The interruptions will take place between 6 a.m. and 6 p.m., when one side of the bridge will be closed to accommodate a 62-foot crane necessary to assess bridge bearings, said Elizabeth Krische, Western’s Associate Vice-President in charge of Facilities Management. [Read More]

October 18, 2018

A reminder to parking customers that all parking lots remain open during the bridge closure. Medway Lot is accessible from University Drive when entering campus from either Sunset Street or Richmond Street.

The linked map depicts vehicle access points to main campus.

October 10, 2018

THE UNIVERSITY DRIVE BRIDGE WILL BE CLOSED TO ALL MOTORIZED VEHICULAR TRAFFIC

Western University will close University Drive Bridge to all motorized vehicles effective October 18, 2018 for the next few months. It will remain open to pedestrians and cyclists.

The abrupt closing of University Drive Bridge is a result of an engineering firm’s findings that the bridge won’t be able to move as it should during winter’s freeze-thaw cycle.

“Safety is at the forefront of this decision,” said Helen Connell, Associate Vice-President for Communications. “We are working with the City of London, London Transit, emergency services, University hospital and other community stakeholders to communicate the closure and mitigate its impact.”

The decision to close the bridge is based on recommendations from an outside structural engineering firm commissioned to conduct a routine inspection. The inspection found that the structure of the 95-year-old bridge requires repair. 

“Bridges are built to move, expand and contract with temperature and load. The heavier the load, the more damage to structure of the bridge,” said Connell. “We need to close the bridge to make the necessary repairs.” 

univresitydrivebridge.jpg

Maintenance chronology:

November, 1923 - New bridge, crossing the Thames River at Western University, opens to traffic.
2002 - major repairs improve traffic flow and pedestrian safety. Heavy trucks barred from bridge.
2016 - Engineering report recommends repairs, further load limits.
March, 2016 - bridge closes for three days for necessary repairs, is re-inspected; traffic resumes.
October, 2018 - engineering report notes damage to bearings that allow the bridge to flex under traffic load and temperature changes.
As of October 18, motorized traffic will be prevented access; pedestrians and cyclists still permitted.

What the campus community can expect moving forward:

  • Bus traffic will be re-routed on Oct. 15 and the bridge will be closed to all other motorized traffic on Oct. 18. Shuttles that would ordinarily use the bridge while travelling between Western and Brescia, Huron and King’s university colleges will be rerouted
  • Design work will take place to determine exactly what repairs are necessary
  • A contractor will be engaged to do the repairs
  • Planning will take place to determine long-term use and function of bridge in light of over-all traffic management in city and on campus.

LTC bus service changes

LTC maintains a webpage for route changes. General information from that page is located below. Updates will continue to be posted on the LTC website and on this website on an ongoing basis; http://www.londontransit.ca/2018/10/10/university-drive-bridge-detour/.

--- FROM LTC (OCT 10) ---

Effective from first bus out of the garage on Monday October 15, 2018 and until further notice, Routes 6, 13 and 106 will be detoured off the Western University Drive Bridge.

During this time the following detours will be in effect.

Route 6

Northbound- north on Richmond, left on Windermere, left on Perth right on Middlesex to regular route

Southbound– Regular Route

Route 13

Northbound– North on Richmond, left on Windermere, left on Perth, right on the University Hospital Access Road, right on Western, right on Windermere to regular route

Southbound– South on Perth Dr. right on the University Hospital Access Road, right on Western, right on Windermere, right on Richmond to regular route

Route 106

Northbound to 102– north on Richmond, left on Windermere, left on Perth, right on Middlesex to regular route

Southbound from 102– Regular Route

* The following is provided by London Transit Commission (LTC): 